A proposal to establish a Conditional Use Permit (CUP) allowing up to approximately twenty-eight (28)single-family residential and approximately 8.2 acres of open space on the 25.8-acre project site, which is located at 800 Meadowpass Road.

Date Detail Doc
March 4, 2020 Planning Commission: Public Hearing Staff Report 
February 27, 2020 Final Draft EIR  Report 
Final Draft EIR Appendices Part 1 Report
Final Draft EIR Appendices Part 2 Report 
February 5, 2020 Planning Commission: Request for Continuance Staff Report
January 15, 2020
Planning Commission: Request for Continuance
Staff Report
November 6, 2019
Planning Commission: Request for Continuance
Staff Report
September 18, 2019
Planning Commission: Request for Continuance
Staff Report
June 5, 2019
Planning Commission: Project Continued Off-Calendar Staff Report
June 11, 2018

Draft EIR Volume 1

Report
 Draft EIR Volume 2;  Appendicies Part 1:
- Initial Study, Notice of Preparation/Scoping Meeting Comments, Air Quality, Assessment, Habitat Assessment, Tree Survey, Historic Resources Assessment, Geotechnical Assessment, etc.
Report
 Draft EIR Volume 2;  Appendicies Part 2:
- Enviornmental Site Assessment, Standard Urban Stormwater Mitigation Plan, Hydrology and Hydraulics Report, Acoustical Assessment, etc.
Report
 Draft EIR Volume 2;  Appendicies Part 3:
- Traffic Impact Analysis and Public Services & Utilities Correspondence
Report
 Notice of Availability of the Draft EIR is circulated; comment period is 45 days Notice
July 29, 2016 
Administrative Draft of the EIR is completed.
Report
June 13, 2016 The Brookside Project Tentative EIR Schedule Report
N/A
EIR Public Comment Form
Handout
May 18, 2016

The Brookside Project EIR Environmental Scoping Meeting Handout

Handout
The Brookside Project EIR Environmental Scoping Meeting Powerpoint Presentation Presentation
May 9, 2016

The Brookside Initial Study

Report
Notice of Preparation of a Draft EIR and Public Scoping Meeting Notice
December 16, 2015 Planning Commission: Request for Continuance Staff Report
August 5, 2015
Planning Commission: Request for Continuance
Staff Report
June 1, 2015
Project Revision
Plans
October 8, 2014
City Council: Approved Contract with Morse Planning Group

Staff Report

Addendum

May 20, 2014
First Time Submittal of the Project

Plans

Plans Photo Legend