Notice of Amar Rd Street Rehab project from Creekside Dr to Meadow Pass Rd

07/17/17 to 10/31/17

Post Date:07/18/2017 4:26 PM

Walnut Residents,

Below is the baseline construction schedule summary for the Amar Rd Street Rehab project from Creekside Dr to Meadow Pass Rd. Schedule subject to change based on site conditions.

Construction to take place on Amar Road from Meadow Pass Road to Creekside Drive from 07/17/17 to 10/31/17. Weekend intersection work listed below will be under a full closure from Saturday 8:00 AM to Sunday 5:00 PM. Detour routes for the designated intersection closure will be posted in advance on changeable message signs (CMS) and detour signs.

Updated Construction Schedule as of 10/3/17:

- Meadow Pass Rd Intersection Completed

Lemon Ave Intersection Completed

Braes River Intersection Completed

Creekside Drive Intersection work scheduled the weekend of 10/07/17 - 10/08/17.


 Construction Schedule as of 7/18/17: 

- Meadow Pass Rd Intersection work scheduled the weekend of 08/05/17 - 08/06/17.

Lemon Ave Intersection work scheduled the weekend of 09/09/17 - 09/10/17.

Braes River Intersection work scheduled the weekend of 09/16/17 - 09/17/17.

Creekside Drive Intersection work scheduled the weekend of 09/23/17 - 09/24/17.

Weekdays will primarily consist of the road work broken up into phases between intersections. Overall the project completion is scheduled for late October 2017.